The Electricity Company of Ghana (ECG) has published a schedule for planned power outages in parts of the Greater Accra Region from 10th May to 17th May 2021.

It said the outage is to facilitate the work of various contractors on its different lines.

ECG explained that it needs to tie-in the Pokuase Bulk Supply Point (BSP) to GRIDCo’s 330kv transmission line hence the need to shut down the transmission line which will affect the Mallam Bulk Supply Point that supplies power to many households.

Power will be interrupted between 6:00 am and 6:00 pm, as well as 6:00 pm and 6:00, am in more than forty communities grouped into four.

The outage will be experienced by two alternating groups each day until the end of the exercise.

Some of the areas to be affected include Awoshie, Nsakina, Dansoman, Ashalaja, Tuba, Abossey Okai, Dansoman, Tuba, Pokuase ACP Estates, Amasaman, Taifa, Ofankor, Kokrobite, Fadama, Israel and Abeka market.

Check Out Timetable Below:

- Advertisement -
Albert Hydehttps://ghbase.com/
Online Journalist with Ghbase.com || Blogger || Journalistalbert@gmail.com

Leave a Reply

Latest News

Matilda Asare lands herself in big trouble after saying there is nothing to be fixed in this country

Matilda Asare is now on the receiving end of insults from social media users over comments she made on...

Top Stories

More Articles Like This